We mine by open-pit strip mining across two blocks, at an average stripping ratio of 7.8 : 1.

Photo: Sandrerro · CC BY-SA 3.0

From land to coal

Every mining block goes through the same sequence, including a reclamation stage planned from the start.

  1. 01

    Land clearing & topsoil

    Vegetation is cleared and the topsoil is stripped and stored for reclamation.

  2. 02

    Overburden removal

    Overburden is dug by excavator and moved to dump areas or backfill.

  3. 03

    Coal mining

    Coal seams 2–6 m thick are cleaned and dug with smaller excavators to avoid dilution.

  4. 04

    Haul to ROM

    Coal is hauled to the ROM stockpile, crushed to 0–50 mm and sampled.

  5. 05

    Backfill & reclamation

    Mined-out pits are backfilled, covered with topsoil and planted with cover crops and native trees.

Main fleet

The fleet is operated together with two mining contractors under HBR safety standards.

Main heavy-equipment fleet at the Tenggarong Seberang site
EquipmentClassUnitsRole
Hydraulic excavator200 t6Overburden stripping
Hydraulic excavator100 t14Overburden & coal
Mining haul truck100 t38Overburden haulage
Articulated dump truck40 t24Coal haulage to ROM
BulldozerD9 / D1012Dumps & land shaping
Motor grader16 ft6Mine road maintenance

Dummy data for design purposes.

A wheel loader and conveyor working at the floor of an open-pit mine

Photo: Carol M. Highsmith / Library of Congress · Public domain

Planning built on data

Our geological model is built from more than 1,850 drill holes and updated every year. Reserves are reported by an Indonesian Competent Person (CPI) under the KCMI code.

Mine plans run from life-of-mine down to weekly schedules, tracked by a fleet management system that logs every load-and-haul cycle.

Measured & indicated resources
210 million tonnes
Mineable reserves
96 million tonnes
Drill holes
1,850+
Mine life
To 2040