Milestones

  1. Company founded

    PT HBR Indo Gemilang is established in Samarinda and granted an exploration licence in Tenggarong Seberang district.

  2. Production-stage licence

    Following approval of the feasibility study and environmental impact assessment (AMDAL), an 8,750 ha production-stage licence is issued.

  3. First shipment

    Commercial production starts at the North Block pit. First-year output reaches 0.6 million tonnes.

  4. 38 km haul road

    The dedicated haul road is completed, taking all coal traffic off public roads.

  5. Mahakam River jetty commissioned

    The company's special terminal starts serving 300 ft barges at 20,000 tonnes per day.

  6. ISO 14001 & ISO 45001 certified

    Environmental and occupational health & safety management systems are independently certified across all operations.

  7. Output passes 4 million tonnes

    The South Block pit reaches full operation and the GAR 5,200 product enters the market.

  8. 1,240 ha reclaimed

    Post-mining reclamation reaches 1,240 ha, with more than 610,000 native seedlings planted since 2014.